Voestalpine HBI Facilities Dock Project

A.H. Beck installs 382 drilled shafts for an unloading dock in the Voestalpine HBI facility in Corpus Christi, Texas

Owner: Voestalpine Texas LLC

Contractor: Bo-Mac Contractors LTD

Location: Corpus Christi, Texas

Solution: Deep Foundations

Industry: Industrial

Techniques: Drilled Shafts

Owner: Voestalpine Texas LLC

Contractor: Bo-Mac Contractors LTD

Location: Corpus Christi, Texas

Solution: Deep Foundations

Industry: Industrial

Techniques: Drilled Shafts

A.H. Beck installs 382 drilled shafts for an unloading dock in the Voestalpine HBI facility in Corpus Christi, Texas

Overview:

The project required 382 drilled shafts 3 feet in diameter and 70 to 100 feet deep for an unloading dock for the Voestalpine HBI facility being built in Corpus Christi Texas. Crews worked 24 hours a day, 6 days a week to complete the work which also included two additional test shafts which were Statnamically tested. The schedule required a continuous work sequence which made access crucial to the success of the project; A.H. Beck was capable of completing its work ahead of schedule.